Abstract
Refueling outages of nuclear power plants are high-consequence operations
in which unplanned schedule extensions
incur significant economic losses.
This paper presents a risk-informed outage scheduling and decision-support
framework developed to address the principal
limitations of current outage management tools.
First, outage scheduling is formulated as a
Resource-Constrained Project Scheduling Problem (RCPSP) that enforces workforce
availability, shared equipment access, radiation dose budgets, consumable inventories, plant
system isolation mutual-exclusion rules, and regulatory surveillance windows as hard constraints,
capturing the resource contention that critical path methods leave to manual resolution.
Second, schedule uncertainty is quantified by constructing empirical activity
duration distributions from historical work order records retrieved by semantic similarity, then
propagating these distributions through the resource-constrained scheduling model via Monte
Carlo simulation to produce completion risk curves, activity criticality indices, and schedule
path sensitivities. Third, a decision-support module evaluates emergent work findings
encountered during outage execution, combining knowledge-graph-based schedule impact
assessment with evidence-traceable \mbox{ESCALATE\,/\,PROCEED\,/\,DEFER} recommendations
for the outage coordinator. Applied to a 66-task PWR refueling outage test case,
the choice of scheduling priority rule alone changes the projected outage duration by
71 hours (a \$4.4 million difference) while automated replanning after a simultaneous crew disruption
and scope addition completes in under one second.
These results demonstrate that risk-informed scheduling makes visible decision consequences
that deterministic critical path methods cannot expose.
in which unplanned schedule extensions
incur significant economic losses.
This paper presents a risk-informed outage scheduling and decision-support
framework developed to address the principal
limitations of current outage management tools.
First, outage scheduling is formulated as a
Resource-Constrained Project Scheduling Problem (RCPSP) that enforces workforce
availability, shared equipment access, radiation dose budgets, consumable inventories, plant
system isolation mutual-exclusion rules, and regulatory surveillance windows as hard constraints,
capturing the resource contention that critical path methods leave to manual resolution.
Second, schedule uncertainty is quantified by constructing empirical activity
duration distributions from historical work order records retrieved by semantic similarity, then
propagating these distributions through the resource-constrained scheduling model via Monte
Carlo simulation to produce completion risk curves, activity criticality indices, and schedule
path sensitivities. Third, a decision-support module evaluates emergent work findings
encountered during outage execution, combining knowledge-graph-based schedule impact
assessment with evidence-traceable \mbox{ESCALATE\,/\,PROCEED\,/\,DEFER} recommendations
for the outage coordinator. Applied to a 66-task PWR refueling outage test case,
the choice of scheduling priority rule alone changes the projected outage duration by
71 hours (a \$4.4 million difference) while automated replanning after a simultaneous crew disruption
and scope addition completes in under one second.
These results demonstrate that risk-informed scheduling makes visible decision consequences
that deterministic critical path methods cannot expose.
| Original language | American English |
|---|---|
| State | Published - Jul 19 2026 |
| Event | PSAM 2026 - Pittsburgh, United States Duration: Jul 19 2026 → Jul 24 2026 |
Conference
| Conference | PSAM 2026 |
|---|---|
| Country/Territory | United States |
| City | Pittsburgh |
| Period | 07/19/26 → 07/24/26 |
Keywords
- outage management
- resource-constrained project scheduling
- schedule risk
- emergent work
INL Publication Number
- INL/CON-26-93319
- 218554
Fingerprint
Dive into the research topics of 'Risk-Informed Resource-Constrained Scheduling for Refueling Outage Management'. Together they form a unique fingerprint.Cite this
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver