TY - GEN
T1 - Performance of the electron LINAC for race at UT Austin
AU - Braisted, J.
AU - Folkman, K.
AU - Hurst, B.
AU - Tillman, D.
AU - O'Kelly, D. J.
AU - O'Kelly, S.
PY - 2007
Y1 - 2007
N2 - A 20-MeV LINAC, constructed at the Idaho Accelerator Center at the Idaho State University, was installed in a beam port of the 1.1 MW University of Texas at Austin (UT Austin) Mark II TRIGA research reactor. This installation was part of a Reactor-Accelerator Coupling Experiments (RACE) Project to examine the sub-critical multiplication of a reactor core driven by a LINAC. The performance of the LINAC, as measured by the observed reactor power, degraded over the three-month experiment period. Performance of the LINAC on any single day was observed to be approximately constant. Another power supply was included as part of the installation to help increase the power output of the LINAC. The immediate effect of the new power supply was to increase the maximum observed reactor power, but once again the reactor power continued to decrease with time. Several components of the LINAC were tested and monitored to determine the cause of the decreasing performance. One of the suggestions for the loss of beam was an over-working RF driver. However, due to time constraints, the RF driver was not re-tuned while at the UT Austin facility. Lessons learned from these experiments demonstrate the need for full-time, experienced accelerator operators for beam diagnostics and greater time available for diagnostics.
AB - A 20-MeV LINAC, constructed at the Idaho Accelerator Center at the Idaho State University, was installed in a beam port of the 1.1 MW University of Texas at Austin (UT Austin) Mark II TRIGA research reactor. This installation was part of a Reactor-Accelerator Coupling Experiments (RACE) Project to examine the sub-critical multiplication of a reactor core driven by a LINAC. The performance of the LINAC, as measured by the observed reactor power, degraded over the three-month experiment period. Performance of the LINAC on any single day was observed to be approximately constant. Another power supply was included as part of the installation to help increase the power output of the LINAC. The immediate effect of the new power supply was to increase the maximum observed reactor power, but once again the reactor power continued to decrease with time. Several components of the LINAC were tested and monitored to determine the cause of the decreasing performance. One of the suggestions for the loss of beam was an over-working RF driver. However, due to time constraints, the RF driver was not re-tuned while at the UT Austin facility. Lessons learned from these experiments demonstrate the need for full-time, experienced accelerator operators for beam diagnostics and greater time available for diagnostics.
UR - https://www.scopus.com/pages/publications/58349105366
M3 - Conference contribution
AN - SCOPUS:58349105366
SN - 0894480545
SN - 9780894480546
T3 - 8th International Topical Meeting on Nuclear Applications and Utilization of Accelerators, ACCAPP'07
SP - 881
EP - 884
BT - 8th International Topical Meeting on Nuclear Applications and Utilization of Accelerators, ACCAPP'07
T2 - 8th International Topical Meeting on Nuclear Applications and Utilization of Accelerators, ACCAPP'07
Y2 - 29 July 2007 through 2 August 2007
ER -