TY - GEN
T1 - Impact of distributed energy resource's ride-through and trip settings on PJM's footprint
AU - Bhattarai, Rojan
AU - Levitt, Andrew
AU - Ramasubramanian, Deepak
AU - Boemer, Jens C.
AU - Kang, Ning
N1 - Funding Information:
ACKNOWLEDGMENT The work of Rojan Bhattarai was supported by the Advanced Grid Research and Development program at the U.S. Department of Energy, Office of Electricity. EPRI provided guidance on the study method and supported in the interpretation of the study results. The development of PJM reliability guideline on minimum DER ride-through requirements is being supported by EPRI. Special thanks to Guenter Conzelmann of Argonne National Laboratory for his support throughout this work.
Publisher Copyright:
© 2020 IEEE.
PY - 2020/8/2
Y1 - 2020/8/2
N2 - As the spread of distributed energy resources invisible from a transmission planner is on the rise, possible lack of ride-through capability and miscoordinated trip settings of these new inverter-based resources can lead to reliability issues for bulk power system operation. This paper presents the finding of a study conducted by PJM to understand the reliability impact of DER ride-through and trip clearing time settings of DER connected to its eastern Mid-Atlantic area. The outcome of this study can be used in the formulation of a regional reliability guideline for ride-through and minimum trip clearing time performance during abnormal frequency and voltage conditions for DER connected in PJM's footprint.
AB - As the spread of distributed energy resources invisible from a transmission planner is on the rise, possible lack of ride-through capability and miscoordinated trip settings of these new inverter-based resources can lead to reliability issues for bulk power system operation. This paper presents the finding of a study conducted by PJM to understand the reliability impact of DER ride-through and trip clearing time settings of DER connected to its eastern Mid-Atlantic area. The outcome of this study can be used in the formulation of a regional reliability guideline for ride-through and minimum trip clearing time performance during abnormal frequency and voltage conditions for DER connected in PJM's footprint.
KW - Distributed energy resources
KW - Momentary cessation
KW - Ride-through
KW - Ride-through reliability
KW - Trip
UR - https://www.scopus.com/pages/publications/85099169505
U2 - 10.1109/PESGM41954.2020.9281948
DO - 10.1109/PESGM41954.2020.9281948
M3 - Conference contribution
AN - SCOPUS:85099169505
T3 - IEEE Power and Energy Society General Meeting
BT - 2020 IEEE Power and Energy Society General Meeting, PESGM 2020
PB - IEEE Computer Society
T2 - 2020 IEEE Power and Energy Society General Meeting, PESGM 2020
Y2 - 2 August 2020 through 6 August 2020
ER -