T1 - Data Analytics Methods to Measure Plant Outage Resilience
AU - Mandelli, Diego
AU - St. Germain, S.
AU - Wang, Congjian
AU - Chen, E.
AU - Mapes, J.
AU - Al Rashdan, A.
AU - Lawrence, Svetlana
N1 - Publisher Copyright:
© 2025 AMERICAN NUCLEAR SOCIETY, INCORPORATED, WESTMONT, ILLINOIS 60559.
PY - 2025/6/15
Y1 - 2025/6/15
N2 - Every 18 or 24 months, nuclear power plants (depending on plant configuration, pressurized- or boiling-water reactor, respectively) undergo an outage period where the plant is taken offline and a large number of maintenance and surveillance activities (that cannot be performed while plant is running) are performed in typically 2-3 weeks. Planning a plant outage is very challenging since all the activities must be performed in the shortest amount of time given available resources (typically contractor crews hired for the duration of the outage). Consequently, plant outages can be costly due the loss of power generation and crew costs and so there is a need to maximize resource usage in the outage planning phase and reduce the risk of outage delays. This paper addresses these needs by providing a set of analytical methods designed to analyze a plant outage schedule and identify critical elements based on available resources (time and crews). These methods are based on natural language processing and optimization algorithms. In this respect, we have developed two classes of methods: one that focuses on the time resource and how variability in the time to complete outage tasks may impact outage delays and one that minimizes the risk of outage delays by integrating available resources to assess when daily activities should be performed.
AB - Every 18 or 24 months, nuclear power plants (depending on plant configuration, pressurized- or boiling-water reactor, respectively) undergo an outage period where the plant is taken offline and a large number of maintenance and surveillance activities (that cannot be performed while plant is running) are performed in typically 2-3 weeks. Planning a plant outage is very challenging since all the activities must be performed in the shortest amount of time given available resources (typically contractor crews hired for the duration of the outage). Consequently, plant outages can be costly due the loss of power generation and crew costs and so there is a need to maximize resource usage in the outage planning phase and reduce the risk of outage delays. This paper addresses these needs by providing a set of analytical methods designed to analyze a plant outage schedule and identify critical elements based on available resources (time and crews). These methods are based on natural language processing and optimization algorithms. In this respect, we have developed two classes of methods: one that focuses on the time resource and how variability in the time to complete outage tasks may impact outage delays and one that minimizes the risk of outage delays by integrating available resources to assess when daily activities should be performed.
KW - natural language processing
KW - Outage
KW - resilience
KW - schedule optimization
UR - https://www.scopus.com/pages/publications/105022084175
UR - https://www.ans.org/pubs/proceedings/article-59000/
U2 - 10.13182/NPICHMIT25-46935
DO - 10.13182/NPICHMIT25-46935
M3 - Conference contribution
AN - SCOPUS:105022084175
T3 - Proceedings of Nuclear Plant Instrumentation and Control and Human-Machine Interface Technology, NPIC and HMIT 2025
SP - 1387
EP - 1397
BT - Proceedings of Nuclear Plant Instrumentation and Control and Human-Machine Interface Technology, NPIC and HMIT 2025
PB - American Nuclear Society
T2 - 2025 Nuclear Plant Instrumentation and Control and Human-Machine Interface Technology, NPIC and HMIT 2025
Y2 - 15 June 2025 through 18 June 2025
ER -